Construction is underway in Moffat on our Fibre To The Home Network. Construction will begin in Mid April 2019 and continue until completion in the summer of 2019.
Project Overview
Standard Broadband’s FTTH construction was started in 2018 and will be completed during the spring and summer 2019. Below you will find ongoing updates and information about specific areas or work and when service will be available. If you have any questions please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. Alternatively you may complete the contact form on this page.
Moffat FTTH Construction Plans PDF – This plan outlines where backbone infrastructure will be placed. Orange ducts will be placed at a depth of .76M and are generally between 1-2M off of the property line toward the road way. There is no construction located on private property.
Ongoing Updates
Aug 2 2091 – Update
Our FTTH construction in Moffat has been completed with the exception of a small portion of homes along 15 Side Road. Service is now available to homes on the following streets.
15 Side Road – All homes between First Line Nassagaweya and Second Line Nassagaweya
15 Side Road – West of First Line Nassagaweya to 1273 15 Side Road
Second Line – between 15 Side Road and Kean Hill Dr
First Line – North of 15 Side Road to 11106 First Line
First Line – South of 15 Side Road to 10621 1st Line
Country Lane Ct – All Homes
Cunningham Ct – All Homes
Cedar Trail – All Homes
Kean Hill Dr – All Homes
Homes along 15 Side Road with addresses between 1091 and 1219 will receive service in the coming weeks. We are working with our engineering firm to complete a new design for these homes as our current creek crossing design is not achievable due to ground conditions. We apologize for the delay to these homes and will have an update in the next few weeks.
Our crew will be completing restoration work along 15 Side Road over the next two weeks where work was done to install the new underground infrastructure.
If you have any questions related to physical construction please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. For sales information our customer service team is available at 1-866-569-4147.
July 15 2019 – Update
Construction has been completed and service is now available to all the homes on the following streets:
Second Line – between 15 Side Road and Kean Hill Dr
First Line – North of 15 Side Road to 11106 First Line
Our crew will be completing restoration work along First Line over the next two weeks where work as done to install the new underground infrastructure. We will be starting our construction work along 15 Side Road west of First Line on Monday July 22nd and anticipate approximately 1 week for construction.
If you have any questions related to physical construction please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. For sales information our customer service team is available at 1-866-569-4147.
June 14 2019 – Update
Construction has been completed and service is now available to all homes on the following streets:
Cunningham Ct – Completed and service is available now.
Cedar Tr – Completed and service is available now.
Kean Hill Drive – Completed and service is available now.
Our crew will be working this week on Second Line between Kean Hill and 15 Side road and service will be available starting on June 26th.
We will begin construction on First Line North of 15 Side Road on June 27th and anticipate service being available to customers around July 10th. We are on track to also start construction along 15 Side Road West of First Line around July 15th.
If you have any questions related to physical construction please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. For sales information our customer service team is available at 1-866-569-4147.
May 31 2019 – Update
Our team has completed construction along Cedar Tr and service is now available to all homes. Please visit our online sign up page to start the installation process and our customer service team will be n touch to schedule your activation.
Below is our updated time line by street:
Cunningham Ct – Completed and service is available now.
Cedar Tr – Completed and service is available now.
Kean Hill Drive – Pending completion by June 10th and service will be available by June 17th.
Second Line between Kean Hill and 15 Side Road – June 12th for construction to start
First Line North of 15 Side Road – June 24th for construction to start
15 Side Road West of First Line – July 15th for construction to start
If you have any questions related to physical construction please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. For sales information our customer service team is available at 1-866-569-4147.
May 17 2019 – Update
With the weather this spring we have been delayed on some of our construction. Our team will be working this week to complete our network build along Cedar Trail. We anticipate completing all work by May 24th and will be able to start installations late the week of May 27th. Please visit our online sign up page to start the installation process and our customer service team will be n touch to schedule your activation.
Below is a new tentative completion schedule by street.
Cunningham Ct – Completed and service is available now.
Cedar Tr – Construction to be completed by May 24th, service available as of May 30th.
Kean Hill Drive – Construction to start May 29th, service estimated being available for June 12th
Second Line between Kean Hill and 15 Side Road – June 10th for construction to start
First Line North of 15 Side Road – June 17th for construction to start
15 Side Road West of First Line – July 2nd for construction to start
If you have any questions related to physical construction please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. For sales information our customer service team is available at 1-866-569-4147.
May 3 2019 – Update
Mother nature has not been on our side very much this week but our team has completed all construction work along Cunningham Ct and we are now pleased to announce that service is available to all homes on Cunningham Ct. Installations are starting next week May 6th please visit our online sign up page to start the installation process and our customer service team will be n touch to schedule your activation.
During the week of May 6th 2019 our team will continue construction along Cedar Tr and then Kean Hill Dr. We anticipate installations starting the week of May 20th 2019.
If you have any questions related to physical construction please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca. For sales information our customer service team is available at 1-866-569-4147.
April 19 2019 – Update
Our construction team has been working along 15 Side Road and Cunningham Ct. We have completed all work along 15 Side Road and our fibre optic backbone cable has been installed up to the corner of Cedar Trail / Cunningham Ct. This we will be continue to work on construction along Cunningham Ct, we anticipate that construction to be completed by April 26th allowing us to commence installations to homes on Cunningham Ct as of May 6th. If you have not already done so please visit our online sign up page to ensure your home is connected to the network.
Our team will also start restoration work where construction has taken place along Cunningham Ct this week and sod / seed will be placed in about two weeks time in areas where grass was disrupted. Upon completion of the initial restoration we will be proceeding along Cedar Tr.
If you have any questions please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca.
April 12 2019 – Update
Many of you will notice that this week flags and paint markings have been placed in the area. These flags and markings are legally required before construction of any kind can begin. They are placed by the other utility companies to show where their underground infrastructure is located. The paint will wash off and our crew will remove flags upon completion of work in the area.
Work commencing next week will consist of the following:
Country Lane Ct, 1st Line Nassagaweya and 15 Side Road (From rail lines to 1st Line) will have any service drop wires that are still above ground near the ditches in the municipal right of way buried in the ground. Along with this we will be completing our restoration work and preparing to have seed and sod placed once the temperature warms up past freezing.
Cunningham Court will see our construction crews working to place the orange duct in the ground in areas where it is currently sitting on the surface. We will also be completing the remaining duct installation starting next week and installing the fibre optic cables in the duct. Once this work is completed we will be able to commence customer installations.
If you have any questions please contact our construction hot line at 1-866-304-9117 or via email at ftthconstruction@standardbroadband.ca.
April 5 2019 – Update
Construction will begin on the following streets in or around April 15th 2019. It is anticipated that from the dates below it will take approximately two weeks to complete each street. Upon completion of work on the street service will be available and installations will begin. Please ensure you have signed up on our web site to book your installation.
Cunningham Court – April 15th 2019
Cedar Trail – April 22nd 2019
Kean Hill Drive – April 29th 2019
First Line North of 15 Side Road – May 20th 2019
15 Side Road West of First Line – June 3rd 2019
Installations will commence per street as each street is completed.
Please contact our customer service team if you have any questions they can be reached at 1-866-569-4147.