Current Status: Construction Underway
Oct 15, 2021
Construction on our Fibre To The Home service in the Hamlet of Ospringe, Erin Ontario has begun. Our crews will be working on the following streets over the next 4-6 weeks. We anticipate having service available by Nov 30, 2021. If you have not signed up online already please visit our online sign up page or click the red Sign Up Now button located on the top right of this page to ensure our new all fibre optic service is connected to your home.
Below is our planned construction schedule.
Oct 19 – Oct 28 – Stewart Drive
Oct 29 – Nov 5 – Anderson Cl and Grundy Ct
Nov 8 – Nov 12 – Second line from Wellington Road 124 to Anderson Cl
Nov 15 – Nov 19 – Wellington Road 124
During our construction our team will strive to keep construction mess to a minimum and we will complete full restoration upon construction completion.