Standard Broadband Puslinch Network Build
Project Updates
Our fibre optic network currently provides service to over 500 homes in the Township of Puslinch. We are actively expanding our network throughout 2023. Use the MAP below to identify your project area and then select it from the drop down options to learn more about our build on your specific street.
Service Area
Project Area: Puslinch-01 - Yellow Streets
Victoria Rd S – Serena Lane to Maltby Rd E.
Backbone duct installation has been completed along Victoria Rd S from Serena Lane to Maltby Rd E. Our team will be completing the fibre optic installation along Victoria Rd S in February and service will be available to the homes between Serena Lane and Maltby Rd E at the beginning of March 2023. At this time addresses have been added to our online sign up and form. After you have completed the online sign up one of our customer service team will contact you to schedule the installation of our service wire (the wire that connects your home or business to the network).
Maltby Rd E – Concession Rd 11 to Watson Rd S
Homes located along Malbty Rd E between Concession Rd 11 and Watson Rd S will have service available for at the beginning of March 2023. At this time addresses have been added to our online sign up and form. After you have completed the online sign up one of our customer service team will contact you to schedule the installation of our service wire (the wire that connects your home or business to the network).
Maltby Rd E – Watson Rd S to Victoria Rd S
Construction of our backbone will take place in March 2023 and service will be available near the beginning of April 2023. When construction begins the addresses of the homes and businesses along this section will have their addresses added to our system and at that point will be able to sign up online.
Project Area: Puslinch-02 - Orange Streets
Backbone construction has been completed on the following streets and customers may now sign up online for service.
Watson Rd S – Between Glenhoml Dr and the river.
Cooks Mill Rd – Between Watson Rd S and the river.
Glenholm Dr
Cooks Mill Rd – Between our existing service and the river.
After you have completed the online sign up one of our customer service team will contact you to schedule the installation of our service wire (the wire that connects your home or business to the network).
Service will be activated in mid February 2023, we are currently waiting on a small portion of fibre to be installed along 8 hydro poles over the river. This work was scheduled for December however due to weather delays hydro has rescheduled the work for the first week of February.
Please use our online form to complete your sign up, if you have already completed the online form and have had your drop cable installed our team will contact you the first week of February 2023 to schedule your in-house / office installation and activation.
Project Area: Puslinch-03 - Purple Streets
Construction will begin in the project area the first week of February 2023. Construction in the project area will take approximately 90 days. Service will be available to homes and businesses on each street as they are completed. Homes and Businesses will be notified prior to construction commencing with more details and timelines for their specific street. Our planned schedule order of construction by street is below.
Construction will take place in the following order:
Arkell Rd – Watons Rd S to Puslinch-Nassagaweya Townline
Wellington Country Road 34 – Between Watson Rd S and Victoria Rd S
Victoria Rd S – Between Wellington Country Road 34 and Maltby Rd S
Old Ruby Lane – Subdivision
Watson Rd S – Between existing completed network and Wellington County Road 34
Project Area: Puslinch-04 - Blue Streets
Construction will take place in this area between May 2023 and September 2023. Service will be available to homes and businesses on each street as they are completed. Homes and Businesses will be notified prior to construction commencing with more details and timelines for their specific street. Our planned schedule order of construction by street is below.
Victoria Rd S – between Wellington Country Rd 34 to Gilmore Rd
Gilmore Rd – between Victoria Rd S to Brock Rd S
Victoria Rd S – between Gilmore to Wellington County Rd 34
McLean Rd
Concession Rd 11 between Wellington County Rd 34 and Small Rd
Darkwood Rd – between Small Rd and Little Road
Wellington County Rd 36 – between Concession Rd 11 and 7811 Wellington County Road 36
Watson Rd S – Between Wellington County Rd 34 and Badenoch Community Centre
Project Area: Puslinch-05 - Red Streets
Construction will take place in this area immediately following completion of project area Puslinc-04 . Service will be available to homes and businesses on each street as they are completed. Homes and Businesses will be notified prior to construction commencing with more details and timelines for their specific street. Our planned schedule order of construction by street is below.
Wellington Country Road 34 – between Watson Rd S and Concession Rd 11
Wellington County Road 34 – between Victoria Rd and Wellington Rd 46
Maltby Road – Between Wellington Road 46 and HWY 6
Wellington Country Road 36 – between Victoria Rd @ and Watson Rd S
Project Area: Morriston-01 - Blue Streets
Construction will take place in this area between February 1, 2023 and March 31, 2023. Service will be available to homes and businesses on each street as they are completed. Homes and Businesses will be notified prior to construction commencing with more details and timelines for their specific street. Our planned schedule order of construction by street is below.
Calfass Rd – Between Settlers Ct and HWY6
Wellington County Rd 36/Badenoch St – Between Ochs St and HWY401
Project Area: Morriston-02 - Purple Streets
Construction will take place in this area between April 1,, 2023 and June 30, 2023. Service will be available to homes and businesses on each street as they are completed. Homes and Businesses will be notified prior to construction commencing with more details and timelines for their specific street. Our planned schedule order of construction by street is below. A large portion of this section had to be re-designed and changed from underground to aerial construction due to insufficient space for new underground ducts. This adjustment has caused some delay to this project area however this are on schedule now for April 1st 2023.
Victoria St and Church St
Wellington County Rd 36/Badenoch St – HWY6 to Ochs St
Ochs St and Back St
Main St
HWY6 from Badenoch St to Church St
Project Area: Morriston-03 - Yellow Streets
Construction will take place in this area immediately following completion of project area Morriston-02 and is expected to take approximately 60 days to complete.