Return To Nassagaweya FTTH Expansion Project Page

Current Status: Phase 1 Construction Underway

July 27, 2021


We are happy to say that things are underway, our initial permits have been issued by the Town of Milton and work is scheduled to begin along Side Road 20 on Aug 9th.

Over the last few weeks we have worked with Ontario One Call to prepare all our locate requests. We have also been engaged with PVS (the firm that will provide the actual locates to us) and they will begin locate work in the next few days.  We have also arranged additional resources on the construction side to ensure that the project remains on target and is completed by Nov 15 2021.

June 27, 2021


Our design and engineering team completed the required drawings for our permit package and the permit requests were submitted to the Town of Milton and Halton Region earlier this month.

Phase 1 construction will begin in the next few weeks as soon as our permits are received.  This phase will consist of construction along the following streets.

Guelph Line – From our existing fibre located at near the Milton Works Yard going north to Side Road 20.
Side Road 20 – From Guelph Line going east to Town Line
Fourth Line – Between Side Road 20 and Side Road 25
Fifth Line – Between Side Road 20 and Side Road 25
Sixth Line – Between Side Road 20 and Side Road 25

Once permits are received a full time line will be released for all four phases of the project. Service will be available as each phase is completed with the entire project being completed by Nov 2021.

May 20, 2021


Our design and engineering team has completed the required drawings for our permit package. Final review is being conducted this week and permit submission will take place next week. Construction of phase 1 is slated to being in early July and take approximately 6 weeks to complete.  Phase 2 will begin construction in August. Phases 3 and 4 will being construction  in mid September and will be built in parallel.

More information will be posted in the coming week.

April 28, 2021


Our Nassagaweya Project is underway and our team is working hard on the background work that is required before construction can begin. Currently our drawings and design for the network has been completed and is just undergoing quality control checks. In about two weeks time the drawings for the first phase of the construction will be submitted to the town and region for permits and construction will being shortly after.

More updates to come next week.

Should you have any questions related to the physical construction work being done in the area please contact our Fibre Construction team directly at ftthconstruction@standardbroadband.ca. Alternatively, you may complete the contact form on this page.

All sales inquiries should be directed to our customer service department who are available sales@standardbroadband.ca or 1-866-569-4147.