Return To Nassagaweya FTTH Expansion Project Page

Current Status: Construction Underway

Service Available On:

Side Road 20 – Between Guelph Line and Nassagweya Town Line
Sixth Line – Between Side Road 20 and Side Road 25
Fourth Line – Between Side Road 20 and Side Road 25
Ennisclare Dr

Sign Up Now


Nov 8, 2021

Our team continues to buildout our network in the community. We are currently work on Guelph Line south of Side Road 20.  Service is now available to homes on the following streets.  If you have not signed up already please use online sign up page to ensure your home is connected to our network.

Service Available On:

Side Road 20 – Between Guelph Line and Nassagweya Town Line
Sixth Line – Between Side Road 20 and Side Road 25
Fourth Line – Between Side Road 20 and Side Road 25
Ennisclare Dr

Upon construction completion on Guelph Line our crews will move to the following areas:

Second Line – Between 15 Side Road and Mowhawk Trail
Mowhawk Trail
Side Road 10 – Between Guelph Line and Second Line
Pineview Trail
15 Side Road – Between Guelph Line and Fifth Line Nassagweya
Fifth Line Nassagaweya – From Side Road 25 to the Dead End south of 15 Side Road.

More details to follow as our progress continues.

Should you have any questions related to the physical construction work being done in the area please contact our Fibre Construction team directly at ftthconstruction@standardbroadband.ca. Alternatively, you may complete the contact form on this page.

All sales inquiries should be directed to our customer service department who are available sales@standardbroadband.ca or 1-866-569-4147.

Oct 15, 2021

Construction continues to move along well. The following streets will have construction completed by Oct 31, 2021 and service will be available for Nov 15, 2021.  If you have not signed up online already please visit our online sign up page.

Side Road 20 – Between Guelph Line and Nassagweya Town Line
Sixth Line – Between Side Road 20 and Side Road 25
Fifth Line – Between Side Road 20 and Side Road 25
Fourth Line – Between Side Road 20 and Side Road 25
Ennisclare Dr

Construction will also begin on the following streets in the next two weeks.

Second Line – Between 15 Side Road and Mowhawk Trail
Mowhawk Trail
Side Road 10 – Between Guelph Line and Second Line
Pineview Trail
15 Side Road – Between Guelph Line and Fifth Line Nassagweya
Fifth Line Nassagaweya – From Side Road 25 to the Dead End south of 15 Side Road.

We anticipate construction to take about 4 weeks to complete with service being available to customers around Nov 30th.

Sept 15, 2021

Construction is underway on our project and things are moving along. We anticipate construction to be completed on the following streets by Sept 30, 2021.

Side Road 20 – Between Guelph Line and Nassagweya Town Line
Sixth Line – Between Side Road 20 and Side Road 25
Fifth Line – Between Side Road 20 and Side Road 25
Fourth Line – Between Side Road 20 and Side Road 25
Ennisclare Dr

Due to work being completed by Halton Region on Guelph line our work has not been able to take place between our existing fibre and Side Road 20. We expect to complete that stretch the first week of Oct 2021.  After that portion is completed customers on the above streets will be able to book their installation and have service activated.

Our construction will continue on the following streets starting the first week of Oct 2021.

15 Side Road between Guelph Line and Sixth Line Nassagaweya
Fifth Line from Side Road 20 to the dead end south of 15 Side Road
First Line Nassagaweya
Second Line Nassagaweya
Mowhawk Trail
Side Road 10
Pineview Trail

Work is expected to be completed on the above roads by end of Oct 2021 and our crews will then move on the last portion of our build with the entire network on track to be completed by Nov 30 2021.

Aug 5, 2021

Our project continues to move along, we have received permits for our phase 1 construction area from both the Town of Milton and the Region of Halton Hills. Our construction team has engaged with PVS Contractors who are the locate service provider for the other underground utilities. PVS will be completing our locate requests this week and construction will begin around Aug 9th, 2021.

Our phase one project area consists of the following streets.

Guelph Line – Between Side Road 20 and the Brookville Public School
Side Road 20 – Between Guelph Line and Nassagweya Town Line
Sixth Line – Between Side Road 20 and Side Road 25
Fifth Line – Between Side Road 20 and Side Road 25
Fourth Line – Between Side Road 20 and Side Road 25
Ennisclare Dr

Construction on our other phases will begin in the near future as well. We have brought in some additional resources to ensure that our network build is completed and on schedule for Nov 15, 2021.

Service will be available to customers in areas where construction has been completed in late Sept 2021, with service being available to all homes by late Nov 2021.

Additional information will be posted to this page as it becomes available.

July 27, 2021

We are happy to say that things are underway, our initial permits have been issued by the Town of Milton and work is scheduled to begin along Side Road 20 on Aug 9th.

Over the last few weeks we have worked with Ontario One Call to prepare all our locate requests. We have also been engaged with PVS (the firm that will provide the actual locates to us) and they will begin locate work in the next few days.  We have also arranged additional resources on the construction side to ensure that the project remains on target and is completed by Nov 15 2021.

June 27, 2021

Our design and engineering team completed the required drawings for our permit package and the permit requests were submitted to the Town of Milton and Halton Region earlier this month.

Phase 1 construction will begin in the next few weeks as soon as our permits are received.  This phase will consist of construction along the following streets.

Guelph Line – From our existing fibre located at near the Milton Works Yard going north to Side Road 20.
Side Road 20 – From Guelph Line going east to Town Line
Fourth Line – Between Side Road 20 and Side Road 25
Fifth Line – Between Side Road 20 and Side Road 25
Sixth Line – Between Side Road 20 and Side Road 25

Once permits are received a full time line will be released for all four phases of the project. Service will be available as each phase is completed with the entire project being completed by Nov 2021.

May 20, 2021

Our design and engineering team has completed the required drawings for our permit package. Final review is being conducted this week and permit submission will take place next week. Construction of phase 1 is slated to being in early July and take approximately 6 weeks to complete.  Phase 2 will begin construction in August. Phases 3 and 4 will being construction  in mid September and will be built in parallel.

More information will be posted in the coming week.

April 28, 2021

Our Nassagaweya Project is underway and our team is working hard on the background work that is required before construction can begin. Currently our drawings and design for the network has been completed and is just undergoing quality control checks. In about two weeks time the drawings for the first phase of the construction will be submitted to the town and region for permits and construction will being shortly after.

More updates to come next week.

Should you have any questions related to the physical construction work being done in the area please contact our Fibre Construction team directly at ftthconstruction@standardbroadband.ca. Alternatively, you may complete the contact form on this page.

All sales inquiries should be directed to our customer service department who are available sales@standardbroadband.ca or 1-866-569-4147.